Clayton Co., GA · Company: QTS · 4 stories · first tracked 2026-07-17 · last activity 2026-07-27
No project stage is auto-generated. What follows is the timeline of record — every entry dated, cited and linked to its source.

Timeline of record

  • Jul 27
    MORATORIUM·Fulton Co., GA
    Stillwater Development has filed to build a gigawatt-scale data center campus called Stillwater Technology Park in Lovejoy, Georgia, south of Atlanta. The project could include up to 15 buildings totaling 3.465 million square feet across 400 acres, with completion of the first phase potentially by 2031.
    Data Center Dynamics · Fulton Co., GA
  • Jul 25
    NEWS·Chatham Co., GA
    OpenAI's proposed $20 billion data center in Effingham County must undergo Georgia's state evaluation process for large-scale developments before construction can begin on the 1,400-acre facility planned for 2028, with a formal DRI form submitted Wednesday containing blank spaces on water usage and environmental impacts.
    thecurrentga.org · Chatham Co., GA
  • Jul 17
    NEWS·Clayton Co., GA
    Headline onlyFOX 5 Atlanta · Clayton Co., GA
  • Jul 17
    HEARING·Clayton Co., GA
    Headline onlyclaytoncountyga.gov · Clayton Co., GA